CoxDENS PP Flex CFS Multi
CoxDENS® PP Flex CLV Multi
This renovation solution is suitable for installing multiple flexible flue pipes with a diameter of 60 mm within an existing CFS duct or shaft.
With CoxDENS® PP Flex CLV Multi, it is also possible to efficiently renovate a CFS system with bends and offsets. Thanks to its flexibility and compact design, it is perfectly suited to modern renovation projects in multi-storey buildings.





Specifications and potential benefits
- Suitable for buildings with 2 to 7 storeys.
- PP flexible pipes Ø 60 mm are used. These are UV-stable.
- The connection to the central heating boiler is Ø 60/100 mm.
- A support bracket must be fitted on every floor, and fixation brackets must be installed every two floors.
- Inside the property, the system is finished with a concentric fire-resistant wall plate.
- As the central heating boiler is connected individually, it is no longer a communal flue.
- As a result, in practice, fewer central heating boilers may need to be replaced.


Procedure for standard CFS:
- Shorten the old outlet.
- Install the roof top.
- Open the shaft.
- Open the CFS duct.
- Fit the support bracket.
- Fit and connect the flexible PP pipe.
- Secure the flexible pipe every 2 storeys.
- Fit the concentric cover plate.
- Seal the shaft with a fire-resistant wall plate.
- Fit the concentric fire collar.
- Apply the wall plate sticker, also known as the shaft ID.
- Fit the outlet terminal.
- Clean or seal the old CFS drain trap.
Procedure for a constructed duct (shunt):
- Modify the old outlet.
- Install the new roof top.
- Open the shaft.
- Fit the support bracket.
- Fit and connect the flexible PP pipe.
- Secure the flexible pipe every two storeys.
- Close the shaft with a fire-resistant wall plate.
- Fit the concentric fire collar.
- Apply the wall plate sticker, also known as the shaft ID.
- Fit the outlet terminal.